Gray's Beach Park Playground Rebuild Project
Gray’s Beach Park Playground Updates:
Due to State and Federal funding grant award and resources, the project needed to be completed in phases.
Phase 1 of the Gray’s Beach Park Playground project site work for the drainage structure installations to assist in alleviating water drainage issues completed.
Remaining portion of Phase 1 construction underway. Some delays in equipment parts; due to the current volatility of the marketplace. Once the parts have been received and installed, Phase 1 will be complete and Playground will open.
Phase 2 of construction is anticipated to begin in July. This will involve installation of the Poured In Place surfacing, and the installation of the final pieces of playground equipment. The playground will close temporarily during Phase 2, which should take about two weeks to complete.
Gray’s Beach Park Stickers for residents are still available to purchase. Non-resident stickers are sold out.