On May 6, 2022, the Department of Public Utilities gave Eversource approval to construct the Carver to Kington Reliability Project. Over the next month Eversource expects to receive all outstanding permits and will be submitting a Grant of Location application to the Town for required segments.
It is anticipated that in late July/early August the Project will prepare for construction with side-trimming and select vegetation removal between Pembroke Road in Kingston and Brook Street in Plympton. Come August, the construction of the new line is projected to begin. Please see the attached letter that will be sent out to abutting properties.
Kingston Reliability Project